Tempo cluster migration

Scheduled Maintenance Report for Grafana Cloud

Completed

The scheduled maintenance has been completed.
Posted Jun 16, 2021 - 21:56 UTC

Update

Outage complete!

Everything is looking good. Scheduled maintenance is still in progress. We will provide updates as needed.
Posted Jun 16, 2021 - 20:47 UTC

Update

We are still seeing some issues on the ingesters, so we will re-deploy this cluster, which will require a 20-30 minute complete outage of the Tempo cluster.

We will update again when this outage is complete.
Posted Jun 16, 2021 - 20:35 UTC

Update

The remediations for the earlier partial write outage appear to be successful.

Scheduled maintenance is still in progress. We will provide updates as needed.
Posted Jun 16, 2021 - 20:10 UTC

Update

We have made some attempted remediations for the earlier partial write outage, and are watching things for about 30 minutes to be sure the remediations are working.
Posted Jun 16, 2021 - 17:51 UTC

Update

Unfortunately, we've run into problems ingesting data during the migration. We are investigating the issue at the moment.
Posted Jun 16, 2021 - 17:26 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 16, 2021 - 13:00 UTC

Scheduled

As a part of planned maintenance, we are migrating Hosted Tracing instances to a new cluster.

Although, we are not planning any downtime, however, a partial service degradation is possible.

If you run into any issues with your Tempo instance, please contact the Support team.

Thank you
Posted Jun 16, 2021 - 12:35 UTC
This scheduled maintenance affected: Traces (GCP US Central - prod-us-central-0: Querying, GCP US Central - prod-us-central-0: Ingestion).